Environmental Permits

Environmental Permits

An environmental permit is a document certifying the right of individual entrepreneurs and legal entities to have a negative impact on the environment and defining the environmental conditions for carrying out their activities (Article 106 of the Environmental Code of the Republic of Kazakhstan). The construction and operation of Category I and II facilities without the corresponding environmental permit are prohibited.

An environmental permit is issued for the operation of each individual Category I and II facility, for the construction (performance of construction and installation work) of such facilities, and for their remediation and/or decommissioning. The Environmental Code of the Republic of Kazakhstan of 2 January 2021 No. 400-VI provides for two types of environmental permits:

  • integrated environmental permit (IEP) – mandatory for the operation of Category I facilities;
  • environmental impact permit – mandatory for the construction of Category I and II facilities, the operation of Category II facilities, and the operation of existing Category I facilities in the cases provided for by the transitional provisions of the Code.

Operators of Category III facilities do not obtain an environmental permit; they submit an environmental impact declaration instead.

Environmental impact permit.

Environmental impact permits for Category II facilities are issued by the local executive bodies of the capital, regions and cities of republican significance, and for Category I facilities (in the cases provided for by the transitional provisions) by the authorized body in the field of environmental protection (Article 120). The application is submitted electronically and must be accompanied by:

  • design documentation for the proposed activity;
  • the conclusion based on the results of the environmental impact assessment (EIA) or the conclusion on the results of the screening of impacts of the proposed activity and, for activities not subject to mandatory EIA, environmental assessment materials under the simplified procedure;
  • draft emission standards and a draft waste management programme (for facility operation);
  • a draft industrial environmental control programme;
  • a draft plan of environmental protection measures for the period of validity of the permit;
  • a draft inventory of stationary emission sources.

Review periods (Article 123): verification of the completeness of the documents – up to 3 working days (local executive body) or up to 5 working days (authorized body); comments are sent to the applicant within 15 working days for Category II facilities and 25 working days for Category I facilities, and must be addressed within 5 and 10 working days, respectively. The permit or a reasoned refusal is issued no later than 30 working days (local executive body) or 45 working days (authorized body) from the date of registration of the application. Shortened periods are established for projects under investment contracts, investment agreements and strategically important projects.

IMPORTANT:

An environmental impact permit for operation is issued for a period until a change in the applied technologies that requires a change in environmental conditions, but for no more than ten years. A change in technology before this period expires will require a new permit.

Integrated environmental permit (IEP).

An integrated environmental permit is mandatory for the operation of Category I facilities and is issued by the authorized body in the field of environmental protection. Operators of other facilities have the right to obtain an IEP voluntarily if approved best available techniques (BAT) conclusions exist for the relevant process or industry (Article 111). The IEP sets technological standards, emission standards, waste accumulation and disposal limits, energy efficiency measures, a waste management programme, an industrial environmental control programme and other environmental conditions.

An application for an IEP is submitted electronically and must contain a description of the techniques applied (proposed), calculations and justifications of the technological standards, and a comparative assessment of the equipment used against the best available techniques. The application is accompanied by the EIA conclusion (or screening conclusion), the justification of technological standards and a draft of emission standards, drafts of the waste management programme and the industrial environmental control programme, a draft inventory of stationary emission sources and, for existing facilities that cannot meet the BAT technological indicators, a draft environmental performance improvement programme.

Review procedure and periods (Article 115):

  • verification of the completeness of the application – 5 working days;
  • state environmental review of the design documentation with respect to facility operation and referral of the application to the interested state bodies (sanitary and epidemiological, sectoral, local executive body, etc.), which submit their conclusions within 25 working days;
  • sending comments to the applicant – within 25 working days after the application is accepted; addressing them – within 10 working days;
  • preparation of the draft IEP with the involvement of internal and external experts – 10 working days; the applicant's position on the draft – 5 working days;
  • issuance of the IEP – within 5 working days after the applicant approves the draft; disagreements over the terms of the permit are considered by an expert commission.

IMPORTANT:

An integrated environmental permit is valid indefinitely. However, when a new BAT conclusion is approved whose requirements the facility does not meet, the operator must, within three months, submit an application to review the IEP (Article 118); if the permit is not reviewed within one year from the date of approval of such a conclusion, it ceases to be valid.

IMPORTANT (transitional provisions):

The requirement for a mandatory IEP has been in effect since 1 January 2025 and does not apply to Category I facilities commissioned before 1 July 2021 (or to facilities whose designs received a positive conclusion of an environmental or independent review before that date) – for them an environmental impact permit is mandatory unless the operator obtains an IEP voluntarily. At the same time, for the proposed reconstruction of such facilities (expansion, technical re-equipment, modernization), obtaining an IEP is mandatory. Integrated environmental permits issued before 1 July 2021 remain valid until 1 January 2031, provided they comply with the BAT conclusions (Article 418).

Best available techniques are the basis of the integrated environmental permit.

Best available techniques (BAT) means the most effective and advanced stage of development of activities and methods of carrying them out, which serves as the basis for setting technological standards and other environmental conditions (Article 113). BAT conclusions are approved by the Government of the Republic of Kazakhstan on the basis of BAT reference documents, which are developed with the participation of technical working groups on the principles of openness, orientation towards the best international practice and consensus among all stakeholders. The conclusions contain emission levels and other technological indicators associated with the application of BAT, as well as monitoring requirements.

The transition to BAT is the key condition for obtaining an IEP. The technological standards included in the permit must correspond to the technological indicators associated with the application of BAT, so the operator needs to conduct a comparative analysis of the techniques applied at the facility, assess the gap against the requirements of the BAT conclusions and justify the technological standards. New Category I industrial facilities are designed, and obtain construction permits, with BAT application taken into account.

IMPORTANT:

If an existing Category I facility cannot meet the technological standards, an environmental performance improvement programme with a schedule of reconstruction and modernization measures must be developed for the IEP (Article 119). The period for its implementation may not exceed four years and cannot be extended, and the progress of implementation is monitored annually by the authorized body. It is therefore advisable to begin preparing for the transition to BAT well in advance – long before the IEP application is filed.

The specialists of SP VECTOR LLP have a very high level of competence in best available techniques. Roman Chestnykh, Director of SP VECTOR LLP, was a member of many technical working groups on the creation of national BAT reference documents and therefore has an insider's understanding of the specifics of BAT and the principles of their implementation. Our Company offers a full range of services for obtaining environmental permits:

  • analysis of BAT applicability and comparison of the techniques used at the facility with the BAT conclusions;
  • justification of technological standards and preparation of draft emission standards;
  • development of environmental performance improvement programmes;
  • development of waste management programmes and industrial environmental control programmes;
  • preparation of applications and support in obtaining IEPs and environmental impact permits, including liaison with the authorized bodies.